The BlueDuct HVAC lines were inspected and passed, so the excavation team began the process of preparing for the concrete subcontractor's slab pour next week. Using a mini bobcat and a series of conveyor belts, the excavators moved fill over the stem walls and then spread it manually up to the level of the BlueDuct. A layer of gravel, then rigid insulation board, comes next. Conduit will be installed east-west within the gravel to provide a pathway to run electric and data lines from one side of the house to the other and also out to the generator and other landscape features.
top of page
bottom of page
Comments