Peter ArmstrongOct 18, 2019DelayBolts and structural steel plates that are needed to move forward were not designed, approved, or fabricated on time... so no pouring this week after all. 12 days out. Bummer.
Bolts and structural steel plates that are needed to move forward were not designed, approved, or fabricated on time... so no pouring this week after all. 12 days out. Bummer.