top of page
Search
Writer's picturePeter Armstrong

Pex Tubing


The radiant heat system installation continues. 5/16" pex tubing, secured with silicone sealant, has been installed in the pre-routed plywood panels throughout the second and attic floors.

The supply and return lines, fed through the floor to the rooms below, will be run to manifolds located throughout.

As you can see, we are working from the top floors down. Mechanical inspections for the first floor are scheduled for later this week. Insulation and Sheetrock to follow.

12 views0 comments

Recent Posts

See All

Comments


bottom of page